Day 7: Thursday, September 27, 2012
Plywood floor for second level.
Day 8: Friday, September 28, 2012
Stairs! Only from the main floor to the second level though, nothing to the basement yet.
Day 9: Saturday, September 29, 2012
When going to the house this morning we were surprised to see the crew out working and so decided to sit and watch for a little while. We were surprisingly very entertained.
As we watched, the crew finished up the framing for the second level. The house is really
beginning to take shape and it has been a lot of fun to be able to walk from room to room.
beginning to take shape and it has been a lot of fun to be able to walk from room to room.
View of the back of the house.
View of the front of the house.
Day 10 - Monday, October 1, 2012
Roof trusses.
More roof trusses.
Day 11 - Tuesday, October 2, 2012
Chris climbed up to what he said was a safe spot to take this picture.
For some reason I just love the way these lines look.
Day 12: Wednesday, October 3, 2012
Finishing up the roof.
Adding the last of the plywood to the roof.
Day 13: Thursday, October 4, 2012
When arriving at the house today we were happy to see that the framing was finally done! Not only does it look complete from the outside, but the construction crew finally added the stairs to the basement, the stairs from the garage into the house, and they poured the concrete for the front porch.
Front porch.
Our House!













3 comments:
This is amazing! So glad you are taking pictures as you go!!! (And glad Chris didn't die taking pictures from his "safe place." :)
Wow!! How exciting! This is really happening. Glad Chris didn't die taking that picture from a "safe" spot. Boys. . .
Hooray!!! It was amazing to see the house come together - a dream coming true. Thanks for letting us watch it through the eye of your camera. The comments were helpful too. I am very excited for you and can't wait to see it in person.
Post a Comment